Golden Ears Pump Station
Project Overview
Location: Maple Ridge, BC
Duration: March 2019 - September 2022
Client: Metro Vancouver Municipal Authority
Services Used
Bulk Excavations
Underground Piping Installation
Environmental Protection Measures
Site Preparation and Grading
Summary & Impact
The Golden Ears Pump Station project was developed with the community's future growth in mind. This project involved extensive excavation and the installation of underground piping to strengthen the region's water infrastructure. Despite challenging terrain and the need to minimize environmental impact, High Road Excavation employed innovative techniques and collaborated closely with environmental consultants to protect the surrounding natural area. The project was completed on schedule and within budget, enhancing the efficiency and reliability of the water supply to the Capilano area.